BSI 15/30313954 DC:2015 Edition
$13.70
BS ISO 16813. Building environment design. Indoor environment. General principles
Published By | Publication Date | Number of Pages |
BSI | 2015 | 24 |
PDF Catalog
PDF Pages | PDF Title |
---|---|
6 | Foreword |
7 | Introduction |
9 | DRAFT INTERNATIONAL STANDARD ISO/FDIS 16813 |
10 | 3.1 acoustic comfort 3.2 competent person |
11 | 3.3 computer analysis 3.4 assumptions 3.5 building environment design 3.6 building control system 3.7 commissioning process 3.10 constraints 3.11 design aids 3.12 design concept 3.13 design criteria |
12 | 3.14 design parameters 3.15 design process 3.16 detail design 3.17 document 3.18 energy conservation 3.19 energy efficiency 3.20 evaluation 3.21 final design 3.22 global cost 3.23 indoor air quality 3.24 life cycle cost |
13 | 3.25 Performance criteria 3.26 project 3.27 requirements 3.28 schematic design 3.29 structure 3.30 sustainability 3.31 thermal comfort 3.32 visual comfort 4.1 General |
14 | 4.2 Project information 4.3 Framework of generation and verification 4.4 Framework of Documentation at Approval 4.5 Harmonization of Architectural and System Design |
15 | 5.1 Stage I: Formulation of project definition 5.1.1 General 5.1.2 Project definition 5.1.3 Opportunities and constraints 5.1.4 Requirements 5.1.5 Assumptions 5.1.6 Philosophy, Ethics and Theories |
16 | 5.1.7 Output – Document I 5.1.8 Evaluation I 5.1.9 Output – Approval of document I 5.1.10 Iteration 5.2 Stage II –Schematic design 5.2.1 General 5.2.2 Input – Background 5.2.3 Output – Document II 5.2.3 Evaluation II |
17 | 5.2.4 Output – Approval of document II 5.2.5 Iteration from conceptual design & schematic design 5.2.6 Iteration from project definition 5.3 Stage III – Detail design 5.3.1 General 5.3.2 Input – Background 5.3.3 Output – Document IIIa 5.3.4 Analysis 5.3.5 Output – Document IIIb |
18 | 5.3.6 Evaluation III 5.3.7 Output – Approval of documents IIIa & IIIb 5.3.8 Iteration into detail design 5.4 Stage IV – Final design 5.4.1 General 5.4.2 Commissioning plan 5.4.3 Commissioning test 5.4.4 Cost estimation 5.4.5 Output – Final document 5.5 End of design |
19 | 8.1 Estimation of primary costs 8.2 Evaluation of design benefits vs. costs as required by client 8.3 Compliance review |
22 | B.1 Issuing or approval of construction documents B.2 Monitoring or supervision of the construction phase B.3 Handover and commissioning of the built works B.4 Post design and post construction commitment |
23 | Bibliography |